Toscana FSRU disconnection successfully completed | CoreMarine

Toscana FSRU disconnection successfully completed

FSRU Toscana control room

Italy, May 2, 2024

CoreMarine has successfully completed riser and mooring disconnection operations for OLT Offshore LNG Toscana, in our most rapid, complex project delivered to date.

The LNG Floating Storage Regasification Unit (FSRU) Toscana, anchored off Livorno, Italy, was required to shut down in early 2024 for extraordinary maintenance.

With the FSRU being one of the major gas terminals for Italy, critical to the country’s energy security, CoreMarine was tasked with preparing an ultra-fast-tracked feasibility study on the disconnection operations. This turned into an equally fast-tracked project to perform riser and mooring disconnection operations.

This was CoreMarine’s most rapid and most complex project to date, with the largest project team we’ve assembled on such short notice. We were thrilled to deliver such a fast, high-quality outcome for OLT Offshore.
- Jason Bayne, CoreMarine Construction Manager

See the full scope of work CoreMarine delivered on the project page:

FSRU Toscana at night

Project: Toscana FSRU disconnection

We worked as an integrated project team with the FSRU Toscana’s operators, ECOS, to engineer and execute the operations.

Go to project page
Toscana 1400x840px
FSRU Toscana drone